IRT-1 Research Reactor Decommissioning Preliminary Plan

Document Type : Original Article

Author

TRIPOLI-LIBYA

Abstract

The 10th African Conference on Research Reactor Safety, Operation & Utilization
IRT-1 Research Reactor Decommissioning: Preliminary Plan

Eng, Usamah Amara Ben Nail1, Eng. Fathi Mohamed Haj2
Tajora Nuclear Research Center
Osa_om_74@yahoo.com1, Fathi_abduo@yahoo.com2

Abstract:
The Tajora Nuclear Research center (TNRC) has two reactors, one of them with a power of 10 MWth and the other Critical Facility Stand with a power of 100 within operation for 41 years, the status of the research reactor is extended shutdown since 2013, for these reasons, the decommissioning plan it became important. The preliminary decommissioning plan consists of actions and steps required as well as the strategies to be adopted for the shutdown of the facility under the technical and administrative, seeking the safety, of health workers and the general public, and minimizing environmental impacts.
This work aims to develop a preliminary plan for decommissioning the research reactor, considering the technical documentation of the system (SAR-Safety Analysis Report), the existing rules of the Libyan Atomic Energy Establishment, as well as regulatory instructions and recommendations of the IAEA.

Keywords


Volume 56, Issue 2 - Serial Number 2
Special Issue: Proceedings of the 10th African Conference on Research Reactor Safety, Operation and Utilization, Cairo, Egypt, 27 – 29 November 2022, organized by the IAEA in cooperation with the EAEA.
January 2023
Pages 122-126